All building projects
CompletedWater & Sanitation

Rainwater Harvesting Tank

Primary School2025
100%
£3,200 raised of £3,200

A 10,000 litre tank collecting from the largest classroom roof, with handwashing stations at the latrines and kitchen. Ends the daily walk to the spring.

Milestones

Tank commissioned
3 April 2026

First full tank after the April rains. Handwashing stations in daily use.

Tank base cast and tank delivered
25 February 2026
Guttering fitted to the Primary 4–5 block
11 January 2026